Chapter 3 - Commissioning
BreezeACCESS VL System Manual
80
3.5 Operation Verification
The following sections describe how to verify the correct functioning of the
Outdoor Unit, Indoor Unit, Ethernet connection and data connectivity.
3.5.1 Outdoor Unit Verification
To verify the correct operation of the Outdoor Unit, examine the LED indicators
located on the bottom panel of the outdoor unit.
The following tables list the provided LEDs and their associated indications.
NOTE
Verifying the correct operation of the Outdoor Unit using the LEDs, as described below, is only
possible after the configuration and alignment processes are completed.
Table 3-4: AU-ODU LEDs
Name Description Functionality
W-LINK
Wireless Link
Indictor
Green – Unit is associated with one or
more SUs
Blinking red – No associations
Off – Wireless link is disabled
Status
Self-test and power
indication
Green – Power is available and
self-test passed.
Blinking Amber – Testing (not ready for
operation)
Red – Self-test failed – fatal error
ETH
Ethernet activity/
connectivity
indication
Green –Ethernet link detected.
Amber – No Ethernet connectivity between
the indoor and outdoor units.